Maidstone Area
Building Regulations were required on this construction, because we
removed the Kitchen wall, installed 4.900 metre length Steel Lintle,
which the new construction intergrated with the Kitchen and became
totally open plan
The Beginning
Building Regulations, and the Building Inspector, played a major role during this construction
The Footings
One metre Footing Required, and a new soakaway
Concrete Footing
The width and depth, had to be checked and Inspected
Drainage
New drainage was laid to accommodate rainwater
Concrete Base
Damproof Membrane, 100mm Celetex Insulation, Concrete Float Floor
The Walls are Rising
100mm Cavity Insulated walls
Catnic Lintles
Three Catnics were used over a single door, The high windows, and the Bi-Fold Doors
Breakthough
Not Yet, But getting prepared, for a 4.900 metre Steel Lintle,
Doorway
The Bi-Fold Doorway is taking shape
The Timber Roof
The Builders, have departed, and the Carpenters have
started.
The Roof
Most of the Timber Beams are installed.
Glass Fibre Roof Installed
Hottest Day of The Year,
Roof Framework
Aluminium Bars
Bi-Fold Doors
Installation of a four pane Bi-Fold Door, with a single
transit door to right.
Plastering the Kitchen Ceiling
Single Door to Enclosed Hall